|
Leak Detection Division Saves
Dollars and Time
28.11.02
Recently,a
contractor
to
the Christchurch City Council discovered a leakage
problem with the new multimillion-dollar leisure pool.
The $12 million pool was nearing completion then,
during
commissioning and testing,
leaks were discovered in the
concrete-encased PVC pipework running underneath it. The
pipes had been tested when they were installed but were
damaged subsequently during the pools
construction.
With the official opening
drawing closer, all options were considered.
First thoughts for repair centred on a complete
excavation of the pool area. As the pool had already
been tiled, this would have been an expensive and
lengthy setback.
However the most favoured
option
was the
use of ADR’s Leak Detection Division’s specialised Casella Spectrascan instruments. The pool was emptied
and staff from ADR used their AquaCorr Correlator,
Ground Microphone and MicroSound acoustic loggers to
locate the leaks. These instruments were able to listen
through the various materials of the pool for the
characteristic sound made by the leaks.
The AquaCorr Correlator
and Ground Microphone were used to find two initial
leaks. These leaks were isolated but
instrumentation
indicated that there was still another, large leak.
Those familiar with leak detection will know that large
leaks often make less noise and are therefore harder to
locate than smaller leaks.
Compounding the
leak
problem
was that sub contractors were completing sections of the
new pool and
two of the existing pools were still in
operation. This situation
created high levels of background noise
that made it impossible to track further leaks using the correlator although the area had been narrowed down to
one side of the wave pool.
To circumvent this
problem, ADR staff decided to use their MicroSound noise
loggers comprising a microphone, battery, transmitter
and special circuitry. These devices were programmed to
monitor and record sounds in the pipework every 5
seconds over a two-hour period between 2:00 am
and 4:00
am.
The loggers were
placed on each of the water outlets in the section of
the wave pool thought to be still leaking. The loggers
were left unattended overnight and next morning the data
was collected.
Analysis
of the data easily located the remaining leak.
This meant that only the
areas showing a positive leak indication were opened up
for repair, which greatly reduced the amount of remedial
work required. This effectively kept the cost and time
of repair to an absolute minimum.
Although the commencement
of operations had to be delayed, the official opening
took place much sooner than first
thought possible.
Thanks, in part, to the effectiveness of the ADR leak
detection staff and
equipment and staff.

|